Logo   WPCA Brookfield, CT



High Meadow Project Construction Schedule

 

The following is the construction schedule for the High Meadow/Ledgewood/Newbury Crossing Sewer Project (HM/LW/NC).

Aug activity: ordering, planning, digging "test pits" and results evaluated. 
Sep activity: completed the run from the Pump Station to Silvermine Road.
Oct activity: started on the piping within HM; Work on the Pump Station.
Nov activity: continued on the piping within HM; Work on the Pump Station.
Dec activity: completed on the piping within HM except for final connections.
Jan activity: started run up Ledgewood Drive towards Lambert Lane.
Feb activity: completed Ledgewood Drive, Lambert Lane, toward Boxwood.
Mar activity: completed more gravity pipe in roadways. 
Apr activity: completed all in-road work including Newbury Crossing.

May activity: Pump Station operational. Some condo units connected.
Jun activity: Completed connecting all but six remaining condo units.
Jul activity: Completed connecting 3 of 6 remaining condo units; restoration.
Aug activity: Completed most of the paving and some restoration remains.
Sep activity: Completed paving and some restoration remains.
Oct activity: Abandonment of septic tanks; Installation on Arbor Dr.
Nov activity: Complete installation on Arbor Dr; Paving all areas.

(Schedule updated Dec 7, 2015) 

Outstanding work:
Week of December 7:
Crack seal and Sealant Westview driveway 
Pavement replacement Westview Cul de sac
Replacement of damaged pole at tennis court
Removal of frames and covers near pool house
Winter:
Move cement curbs in pool parking areas when machines on site for snow removal.

 

PhaseTask AreaStartFinishNotes
PrelimUtility Locating All07-0707-22note
PrelimTest Pits All08-1208-28note
PrelimClearing+Materials Staging All08-1508-25note
1Pump Station HM10-0605-15note
2Force Main + Gravity Lines HM09-0201-05note
3Gravity Lines & Connections HM10-2004-30note
3Connecting to gravity lines HM03-1807-17note
4AGravity Sewer Lines LW03-0207-17note
4BGravity Sewer Lines NC03-1604-07note
4CGravity Sewer Lines NC03-1605-05note
5*Gravity Lines & Connections NC03-1606-30note
6Restoration of Surfaces All10-1509-30note
FinalAbandon Existing Structures All09-0209-30note
AddlConnect Last 3 Units LW09-1410-23note
FinalPaving All11-0111-15note

Expecations:

  • Please do not communicate with the workers on site.

  • If you have any questions or concerns, please direct them to your point of contact person below

    (Do not call the WPCA). These 3 people will then contact the Brookfield WPCA:

    • High Meadow:        Peter Citrone 203-297-7475

    • Newbury Crossing: Gail Bristol 203-770-8410

    • Ledgewood:            Cheryl Peatfield 203-740-9255

  • Construction etiquette:

    • Avoid work areas.

    • Keep your pets leashed at all times.

    • Keep your children off and away from all machinery, stockpiles, materials, etc.

    • Be aware of your surroundings, i.e. uneven surfaces, detours, barricaded areas.

    • Large machinery and trucks have limited visibility and will be entering and exiting

      frequently. Please keep clear.

    • Please respect utility markouts, flagging & construction staking (do not remove or destroy). 

      We ask that all residents and their families, as well as landscaping and maintenance people

      do their best to protect these items.

    • Occasional loud noises are to be expected.

    • You may be asked to temporarily relocate your personal vehicle to facilitate construction.

      Every effort will be made to give you prior notice.

  • Contractor hours are expected to be between 7:00 am and 5:00 pm, Monday through Friday,

    however there may be circumstances that require work outside of these hours.